Nscale is supplied by NVIDIA and supplies Anthropic, Microsoft and NVIDIA.
Each line is 100 MW.an estimate (~)under 50 MW
Compute
Others have contracted from it
16 Mar 2026 Microsoft, Capacity reservation, Capacity: 1.4 GW
A letter of intent, not a definitive agreement, for 1.35 GW of AI compute for Microsoft at the Monarch campus in West Virginia.
18 Sep 2026 Payments of up to about $43.8 billion through December 2033, per Nscale (18 Sep 2026).
5 May 2026 From late 2027, at Start Campus Sines Data Campus.
SEC Form S-1 (registration statement) by Nscale, 18 Sep 2026; Press release by Nscale, 5 May 2026; Press release by Nscale, 14 Apr 2026; and 2 more
Anthropic, Cloud capacity, conditional, Amount: up to $44.6B
Anthropic’s prospectus (S-1/A No. 2): GPU services agreements of August 2026 with wholly owned subsidiaries of Nscale Global Holdings Limited; up to approximately $44.6 billion over terms extending into 2033.
SEC Form S-1 by Anthropic, 10 Nov 2026; SEC Form S-1 (registration statement) by Nscale, 18 Sep 2026
Sites
- Start Campus Sines Data Campus, Sines, Setúbal, Portugal. AI hardware owner; provides reserved capacity, Power: ~40 MW
- Keflavik, Suðurnes, Iceland. AI hardware owner, Power: ~7 MW
- Microsoft Narvik Norway, Narvik, Norway. AI hardware owner (source marks likely); under construction
1 compute cluster
- Loughton, Loughton, United Kingdom. Site owner (Jan 2025); announced, Power: ~90 MW
Power figures are each site’s own.
Suppliers and customers
Figures read 23 Nov 2026. Latest source 22 Nov 2026.
Sources, 4
- Compute control disclosures
- Filings, calls and announcements by either party7 disclosures
- Export-control designations
- Federal Register-anchored designations22 Nov 2026
- Supply-chain relationships
- SEC disclosures, re-derived company disclosures, licensed supply-chain database
- Facility records and their sources
- Known facilities, with each site’s estimate flags
How the figures were made
Suppliers and customers. Records are grouped by counterparty, and counterparties with more current records come first. A line prints without a product where its source doesn’t name one or the description on file has not been tied to that source. Alternative suppliers may exist outside this corpus.
Known facilities. Each site is listed with the relationship its source establishes. A site’s power figure counts as operating capacity, is left out of it with the reason beside the figure, or is not shown; of the 4 sites whose record names Nscale, 2 count as operating capacity, 1 has its power figure left out of it and 1 shows no power figure. A tilde marks a figure the site’s own record marks as estimated.
Compute arrangements. Filings and announcements recording who owns, runs or contracts compute capacity, where this company is one of the parties. Each is graded by its source’s authority, who disclosed it and whether its figure is an estimate. Nscale is a party to between 4 and 5 compute arrangements.
Identity. Variant identifiers are resolved to one organisation before its data is combined.
Identifiers
- SEC CIK
- 2110365
- Scrutica ID
- org-nscale
Name forms resolved to this record: Nscale plc.