Nscale Loughton

TypeAI TrainingStatusAnnouncedWhereLoughton, GBIndexed fromEpoch AI GPU Clusters

Announced; Nscale is recorded as an owner of this site

Nscale’s Loughton AI campus in Essex — the company’s first UK site, whose purchase it announced on 2025-01-13. On 2025-09-16 Nscale and Microsoft announced a commitment on the campus: 50 MW of AI capacity scalable to 90 MW, initially housing 23,040 NVIDIA GB300 GPUs delivered in Q1 2027, with the facility to “play a vital role in providing Microsoft’s Azure services across the UK.” That chip figure supersedes Nscale’s own January 2025 statement that the site could “house up to 45,000 of the latest Nvidia GB200 GPUs” — a site-capacity ceiling rather than a committed deployment. Both figures are Nscale’s: the substrate preserves the January transcription and the displayed chip, FLOP and H100-equivalent values carry the September commitment through the editorial corrections overlay.

Source: Epoch AI GPU Clusters

1/3site roles identified1 site relationship1 finding in the company chain0 export-control designationsFurthest finding: company at site

Date in site records: Sep 16, 2025. Site data: Epoch AI GPU Clusters.

Ownership and operation

Plate I. Site owner, operator and hardware ownerscrutica.com · data to Sep 16, 2025 (derived)

Site owner · last stated Jan 2025

Nscale parent ownership unresolved 1 finding

Which organisation holds the site?

Nscale LoughtonSite

Site owner · last stated Jan 2025 Nscale. “Nscale has confirmed its first UK data centre with the purchase of a site in Loughton.” source

Companies are grouped by their role at the site, with recorded parents above them. No parent companies were found in the ownership data. Further ownership remains unresolved where labelled. Record source: Epoch AI GPU Clusters; authority tier 2. Each role is drawn only as the relationship its own source establishes, listed above; none implies exclusive control of the full site. Ticks count the export-control and government-link findings for each company.
Plate II. Organisations recorded at the sitescrutica.com · data to Sep 16, 2025 (derived)

Capacity customer (announced)

Microsoft Corporation

The organisation's own statement states a planned capacity commitment at the site.

Microsoft Azure services (UK) · from Sep 16, 2025 · Company Press Releases source

One relationship is recorded at Nscale Loughton, labelled “Capacity customer (announced)”.

Export controls and government links

No export-control designations were found in the checked company chains.

Plate III. Export controls and government linksscrutica.com · data to Sep 16, 2025 (derived)
site1A company in the ownership chain is headquartered in the United Kingdomcompany levels
Company at site

Headquarters jurisdiction
A company in the ownership chain is headquartered in the United Kingdom

United Kingdom: Post-Brexit operates its own dual-use control regime via the Export Control Joint Unit (ECJU); UK Sanctions and Anti-Money Laundering Act 2018 underpins targeted measures. Export-control regimes listed for this jurisdiction: Wassenaar Arrangement, UK Strategic Export Controls.

Country is the recorded headquarters location.Linked through the company recorded as holding title to this site.

Triangle: export-control designation or regulatory flag. Square: sovereign capital linkage. Circle: headquarters jurisdiction. Level 1 is a company at the site; higher levels are its parents. 1 finding is recorded; 0 are export-control designations.

Capacity

Reading. Power and acceleratorsscrutica.com · data to Sep 16, 2025 (derived)
90 MW

Facility power

Estimated. Not operating capacity: announced.

not recorded

Power for IT equipment

23,040

Accelerators

58,211 H100-equivalent. Not operating capacity: announced.

Present inventory by partition

withheld Facility status is announced, not operational.

  1. 45,000 × NVIDIA GB200 (estimated)

    status not stated (from the facility status)

    Held: Not present capacity. Part of the inventory has no recognized deployment status.

    Catalogue row; no partition-level source recorded

One partition is held, so no facility figure is derived; the held partition’s count and source remain visible and nothing is substituted for its rate. Rates are the cited dense FP16 figure per accelerator; the sum applies the methodology’s utilization and interconnect assumptions and is a theoretical aggregate, not one job’s throughput. The catalogue figures above are the record’s scalar fields (the source’s transcription, or its recorded correction) and are a different basis.

Power comparison

90 MW is not placed among operating AI Training figures (announced).

Data quality · 1 flag
  • A newer operator disclosure supersedes an earlier statement this record once showed. The substrate row transcribes Nscale’s January 2025 site-capacity ceiling (45,000 NVIDIA GB200). Nscale’s September 2025 release with Microsoft commits 23,040 NVIDIA GB300 delivered in Q1 2027. Displayed chip, FLOP and H100-equivalent values carry the September figure through the editorial corrections overlay; the accelerator-inventory panel renders the corrected count against the substrate’s hardware type, so GB200 may still appear as the model name until an Epoch refresh carries the GB300 line.

Methods and sources

Ownership roles

Title identifies the legal owner of the site; operation identifies who runs it. AI-hardware ownership follows the catalog’s attribution of the machines inside, whose owner may lease the facility.

Each role requires its own attribution. An operator named in a source supplies evidence of operation only.

Parent companies

Ownership checks start with each company named at the site and follow recorded parent relationships. A company holding several roles is checked once. Its linked company page lists the relationships and their sources; further parents may remain undocumented.

Level 1 identifies a company at the site, level 2 its parent, and each further level another parent. Export-control designations and government investments are assigned to the company concerned.

Missing values

Unrecorded roles remain blank. Findings whose company position is unresolved stay in the list with that position labelled unknown.

Publication limits

Subscription corporate data helps identify parent relationships and sovereign investments. Publication is limited to relationship classes and supporting public sources; licensed records, identifiers and values are withheld.

Epoch AI estimates capacity using satellite imagery, permits and corporate disclosures. Its catalog is the source for this site record.

Browse the facilities directory or search the company directory.