Suppose a training agreement requires each government to list its covered facilities and chips. Select US-only, US–China or wider participation to see which public records inspectors could check against those lists.

Participating countries

Capacity measure

Chinese facility records

If China joins, inspectors could also check its list against 56 Chinese facility records.

733 MW recorded across 3 operational sites in China.

Scrutica lists 56 facilities in China across all statuses; 53 have neither a power nor a chip-capacity figure.

  1. Huawei HoringerChina278 MW
  2. VNET Bayin UlanqabChina252 MW
  3. Alibaba ZhangbeiChina203 MW

Country breakdown and missing capacity

CountryOperational sites · MWAll records · missing capacity
United States14,707 MW157 sites1,278 listed1,038 without capacity
China733 MW3 sites56 listed53 without capacity
Malaysia446 MW2 sites22 listed19 without capacity
United Kingdom148 MW8 sites197 listed188 without capacity
France100 MW14 sites301 listed278 without capacity
India89 MW6 sites132 listed117 without capacity
Portugal40 MW1 site13 listed12 without capacity
Italy37 MW8 sites78 listed67 without capacity
Japan36 MW20 sites112 listed84 without capacity
Finland33 MW5 sites31 listed25 without capacity
Showing 10 of 110

Country names open their facility records. “All records” includes every status. “Without capacity” means neither electrical nor chip capacity is recorded. Neither count is a national inventory.

The register contains 16,642 MW across 322 operational facilities with a recorded figure.

This includes 16 operational facilities with no recorded country, accounting for 86 MW. They cannot be assigned to a participating group.

Across all statuses and countries, 3,754 records lack both capacity figures. Operating figures come from operational records only: a campus build-out figure recorded on an operating site is held out, and a reviewed current deployment counts in its place, as at New Carlisle; earlier phases of an operating cluster are held out of accelerator counts.