Anthropic-Amazon New Carlisle

TypeAI TrainingStatusOperationalWhereNew Carlisle, Indiana, USIndexed fromEpoch AI Frontier Data Centers

Operational; Amazon.com, Inc. is recorded as owning the AI hardware inside this site

Description quoted from Epoch AI Frontier Data Centers

Anthropic-Amazon New Carlisle is part of the Anthropic-Amazon Project Rainier collaboration. It is similar to other Amazon locations, forgoing most external cooling infrastructure in favor of direct air based cooling.

Source: Epoch AI Frontier Data Centers, CC BY 4.0

1/3site roles identified1 site relationship1 finding in the company chain0 export-control designationsFurthest finding: company at site

Date in site records: Oct 19, 2026. Site data: Epoch AI Frontier Data Centers.

Ownership and operation

Plate I. Site owner, operator and hardware ownerscrutica.com · data to Oct 19, 2026

AI hardware owner · per catalog

Amazon.com, Inc. parent ownership unresolved 1 finding

Which organisation owns the AI hardware inside it?

Anthropic-Amazon New CarlisleSite

AI hardware owner · per catalog Amazon.com, Inc. Epoch AI's field for who owns the AI hardware, which it defines as not necessarily the owner or operator of the facility. source

Companies are grouped by their role at the site, with recorded parents above them. No parent companies were found in the ownership data. Further ownership remains unresolved where labelled. Record source: Epoch AI Frontier Data Centers; authority tier 2. Each role is drawn only as the relationship its own source establishes, listed above; none implies exclusive control of the full site. Ticks count the export-control and government-link findings for each company.
Plate II. Organisations recorded at the sitescrutica.com · data to Oct 19, 2026

Uses the compute

Anthropic

Named in Epoch AI's field for labs using the compute; it records use, not a lease.

Epoch AI Frontier Data Centers source

One relationship is recorded at Anthropic-Amazon New Carlisle, labelled “Uses the compute”.

Export controls and government links

No export-control designations were found in the checked company chains.

Plate III. Export controls and government linksscrutica.com · data to Oct 19, 2026
site1A company in the ownership chain is headquartered in the United Statescompany levels
Company at site

Headquarters jurisdiction
A company in the ownership chain is headquartered in the United States

United States: Operates the Export Administration Regulations (EAR) and the BIS Entity List under 15 CFR 730–774; deemed-export rules extend reach to foreign nationals on US soil. Export-control regimes listed for this jurisdiction: Wassenaar Arrangement, US EAR (BIS Entity List authority).

Country is the recorded headquarters location.Linked through the company recorded as owning the AI hardware inside this site.

Triangle: export-control designation or regulatory flag. Square: sovereign capital linkage. Circle: headquarters jurisdiction. Level 1 is a company at the site; higher levels are its parents. 1 finding is recorded; 0 are export-control designations.

Capacity

Reading. Power and acceleratorsscrutica.com · data to Oct 19, 2026
1.1 GW

Facility power

Counted in operating totals; recorded-power totals count this campus once, using AWS Project Rainier (New Carlisle, IN).

1.0 GW

Power for IT equipment

Estimated.

not recorded

Accelerators

An estimated 818,428 H100-equivalent.

New Carlisle (AWS Project Rainier / Anthropic) has 3 records, and their power figures are never added together. Across the platform, recorded totals count the marked figure once; operating totals count a member’s figure only if it is operating capacity.

Scope: full build-out · Status: operational · counted in recorded totals

AWS Project Rainier (New Carlisle, IN)

2.2 GW · not operating capacity · Press reporting

Scope: current deployment · Status: operational

Anthropic-Amazon New Carlisle

1.2 GW · operating capacity · Epoch AI Frontier Data Centers

Scope: named cluster · Status: announced

Project Rainier

350 MW · not operating capacity · Epoch AI GPU Clusters

Power comparison

1.092 GW is at the 99th percentile among the 310 operating AI Training records with a reported power figure. These represent 84% of the 369 operating AI Training records tracked; announced, under-construction and campus build-out figures are not ranked. The scale ends at the largest operating figure in this group, 1.276 GW.

Data quality · 1 flag
  • This record’s power figure is withheld from recorded-power totals so the campus counts once; operating totals count it, as the campus’s reviewed current deployment.
    Curator’s working note

    Part of the New Carlisle / Project Rainier campus. This row's power capacity (1,092 MW facility power, 910 MW for IT equipment, Epoch current-deployment estimate) is withheld from recorded-power totals, which count the campus once at its canonical 2,200 MW, the full build-out recorded on AWS Project Rainier (New Carlisle, IN); operating totals count this row, under an editorial review, as the campus's current deployment. GPU/PFLOP figures unaffected.

Methods and sources

Ownership roles

Title identifies the legal owner of the site; operation identifies who runs it. AI-hardware ownership follows the catalog’s attribution of the machines inside, whose owner may lease the facility.

Each role requires its own attribution. An operator named in a source supplies evidence of operation only.

Parent companies

Ownership checks start with each company named at the site and follow recorded parent relationships. A company holding several roles is checked once. Its linked company page lists the relationships and their sources; further parents may remain undocumented.

Level 1 identifies a company at the site, level 2 its parent, and each further level another parent. Export-control designations and government investments are assigned to the company concerned.

Missing values

Unrecorded roles remain blank. Findings whose company position is unresolved stay in the list with that position labelled unknown.

Publication limits

Subscription corporate data helps identify parent relationships and sovereign investments. Publication is limited to relationship classes and supporting public sources; licensed records, identifiers and values are withheld.

Epoch AI estimates capacity using satellite imagery, permits and corporate disclosures. Its catalog is the source for this site record.

Curator’s note on this campus

Three records describe the New Carlisle campus at different stages and scopes. Recorded totals use the 2,200 MW full-build-out figure from the October 2025 CNBC/Amazon reporting, which describes the planned 30-building campus rather than the plant running today. Operating totals use Epoch’s current-deployment estimate instead; CNBC reported seven buildings online. The Project Rainier cluster’s 350 MW figure remains visible for comparison but is excluded from both totals. The cluster record also reports 400,000 accelerators.