TypeAI TrainingStatusUnder constructionWhereSt. Francisville, Louisiana, USIndexed fromSEC EDGAR

No organisation is recorded as holding this site, running it, or owning the AI hardware inside it

Hut 8's AI data centre campus off LA 964 near St. Francisville in West Feliciana Parish, Louisiana, with 330 MW of utility capacity and 245 MW of critical IT capacity leased for 15 years to Fluidstack, with Google backstopping the lease payments. Vertical construction began in the second quarter of 2026, and Hut 8 targets the first data hall for the second quarter of 2027.

Source: SEC EDGAR

0/3site roles identified0 site relationships0 findings · no company identified

Date in site records: Apr 30, 2026. Site data: SEC EDGAR.

Ownership and operation

Plate I. Site owner, operator and hardware ownerscrutica.com · data to Apr 30, 2026
River Bend Data Center CampusSite
Companies are grouped by their role at the site, with recorded parents above them. No company is identified in these roles, so their ownership chains could not be checked.

Export controls and government links

No site owner, operator or hardware owner is identified, so the company checks could not run.

Capacity

330 MW

Facility power

Source-reported power. Not operating capacity: under construction.

245 MW

Power for IT equipment

Source-reported power.

not recorded