South Korea had two systems of 7,656 and 3,056 accelerators in operation by May 2026, against a target of 260,000 for 2030, with 2,424 under way.

National AI Initiative, 2025–2030; the record also covers K-Chips Act

Accelerators7,656 and 3,056 operating; 260,000 promisedby 2030
  • operating
  • pale: not yet operating
  • time elapsed
A full bar is 300,000 accelerators. Each system in operation is a segment of its own, and no total is printed, since two records can describe one machine. The tick marks how much of 2025 to 2030 had passed by 14 May 2026.

Tracked accelerators, as of 14 May 2026

In operation

May 2026: 16 of 72 months

in operation19 points below an even pace

7,656 and 3,056 of 260,000 accelerators

Spent

Jul 2026: all 12 months

spentat an even pace

₩1,460 billion of ₩1,461 billion

₩1,460 billion spent by July 2026, once all 12 months of the budget’s period had run, of the 2025 supplementary budget’s ₩1,461 billion for buying and installing government GPUs.

Up, the share of the target in operation and of the budget spent; across, the share of each one’s period gone.

Systems

Four hardware records; pale rows are announced or under way.

The programme’s systems
AnnouncedGovernment and private companiesNVIDIA GPUs
Under wayKakaoB200
In operationNHN CloudB200
In operationNaver CloudH200

Funding

Funding components
Government
Government~$1.1B
Private
Private
State enterprise

4 components are named in the programme’s sources without an amount.

Sovereign AI Funding

Money on record

Its sources give committed (2025 supplementary-budget GPU procurement).

Chips and rules

Accelerators
NVIDIA’s accelerators are in all four of its systems.Chip makers’ product pages
Fabrication
fabricates the Blackwell and Hopper parts that three of its systems name.Chip makers’ product pages
US export rules
South Korea is in , outside the groups where exporting advanced AI chips needs a licence from the US Bureau of Industry and Security (BIS).Electronic Code of Federal Regulations, 29 Oct 2026
Scrutica’s rating
Scrutica rates the programme’s dependence on NVIDIA hardware and on US technology high, on a scale of none, low, medium and high.A qualitative assessment of the programme’s chips, partners and supplier relationships, as none, low, medium or high

Partners

11 named in the programme’s sources, besides the operators in Systems.

Named in sources
NVIDIA, Samsung Electronics, SK Group, Hyundai, MSIT, Naver, SK Telecom, LG, NCSoft, Upstage, KEPCO

Sources

16 sources
Data
How the figures were made

Operating compute / delivered hardware. Reported operational or delivered: 7,656 NVIDIA B200 (physical hardware); 3,056 NVIDIA H200 (physical hardware). The stage is assigned from reported hardware status, disbursements and commitments.

The 2025 supplementary-budget procurement allocated 13,136 GPUs across NHN Cloud, Kakao and Naver Cloud, with 10,456 reserved for government use. NHN Cloud announced completion of its 7,656 B200 system in May 2026; Kakao reported 2,040 GPUs installed and testing in December 2025 within its 2,424-GPU allocation. ZDNet Korea reported Naver’s 3,056 H200 system in operation in May 2026. Korea’s longer-term targets combine public acquisitions with private-company plans. A separate National AI Computing Center is planned at Haenam.

Caveats on this record, 8

  • MSIT’s July 2025 procurement announcement allocates 10,080 B200 and 3,056 H200 GPUs across three cloud providers. The KRW 1.46T supplementary-budget allocation was reported as approximately US$1.1B. The government-use quantities are subsets of the provider totals.
  • NHN Cloud announced the completed 7,656-B200 system on 13 May 2026, with 6,120 GPUs reserved for government use. Some government-funded resources had been available since 1 April.
  • Kakao’s 29 December 2025 announcement describes 2,040 installed B200 GPUs under final testing, within its 2,424-GPU allocation. It scheduled beta access for 2 January 2026 and gives no status for the remaining 384.
  • Naver’s operational status follows ZDNet Korea’s 14 May 2026 report on its 3,056 H200 GPUs. Provider confirmation of that status is unavailable.
  • Korea Herald reported in December 2025 a 52,000-GPU public-sector target for 2028 within a larger 260,000-GPU public/private plan for 2030. NVIDIA’s October 2025 announcement includes about 50,000 public-sector GPUs and more than 200,000 for private companies, without a completion date. These targets include multiple acquisition programmes.
  • The sovereign-model programme selected five consortia in August 2025. At the January 2026 evaluation, LG AI Research, SK Telecom and Upstage advanced; Naver Cloud and NC AI were dropped, and a further selection round was planned to fill a fourth place.
  • ZDNet Korea reported on 16 June 2026 that the Korea AI Computing Center company had registered the previous week, with its headquarters at Haenam. It reported Samsung SDS’s stake as 30%, the government’s as 29% and Naver Cloud’s as 26.1%. This corporate formation is separate from the 2025 cloud-provider GPU procurement.
  • The AI Basic Act and its Enforcement Decree took effect on 22 January 2026.
Identifiers
Scrutica ID
sovereign-kr
Country code
KR
Name in the record
South Korea: National AI Initiative & K-Chips Act