Sovereign programme record · Canada · 2024–2030

Canada: programme funding and hardware

Canada: Canadian Sovereign AI Compute Strategy / Pan-Canadian AI Strategy / AI for All

The reconciliation

This record has no dollar amount for these funding stages. Programme details and source amounts appear below.

Operating compute / delivered hardware. Reported operational or delivered: 636 NVIDIA A100 SXM4 (40GB) (physical hardware).

Funding components

ComponentKindAmount
Budget 2024: public supercomputer allocation (up to C$705M, March 2025 breakdown)Government—
Budget 2024: commercial data-centre support (up to C$700M)Government—
Budget 2024: Compute Access Fund (up to C$300M)Government—
Budget 2024: expansion of existing infrastructure (up to C$200M)Government—
Budget 2025: sovereign public AI infrastructure (C$925.6M; includes previously provided funding)Government—
AI for All: additional Compute Access Fund funding (C$700M, June 2026)Government—

Hardware on record

ModelCountStatusOrganisation / role
NVIDIA A100 SXM4 (40GB)636OperationalDigital Research Alliance (Narval, Calcul Québec)

Physical hardware: Narval’s A100 partition: 159 nodes with four GPUs each. Primary source

Empanelled partners · 9

PartnerAcceleratorsModelStageSource
Cohere Inc.—NVIDIA (model unspecified)AwardedPrimary source · 2025-03-20

The government finalised a contribution of up to C$240M to Cohere’s C$725M compute project in March 2025. Cohere is the anchor tenant of the Cambridge facility that CoreWeave will build and operate.

  • Programme-level disclosure
CoreWeave—NVIDIA (model unspecified)AwardedPrimary source · 2026-06-05

Will build and operate the Cambridge, Ontario compute facility for which Cohere is the anchor tenant. The C$725M project and federal contribution concern Cohere’s compute expansion.

  • Programme-level disclosure
Digital Research Alliance of Canada——AnnouncedPrimary source · 2025-02-18

Maintains Canada’s research computing, data and software infrastructure. In February 2025, the Alliance said it was scheduled to receive C$85M for AI compute.

Mila (Institut québécois d'intelligence artificielle)——EmpanelledPrimary source · 2025-07-25

Works with Université Laval on the Pan-Canadian AI Compute Environment, which provides dedicated infrastructure for AI research.

  • Programme-level disclosure
Vector Institute——EmpanelledPrimary source · 2025-07-25

Works with the University of Toronto on the Pan-Canadian AI Compute Environment.

  • Programme-level disclosure
Alberta Machine Intelligence Institute (Amii)——EmpanelledPrimary source · 2025-07-25

Worked with the University of Alberta to build Vulcan, a PAICE research computing system launched in April 2025.

  • Programme-level disclosure
Shared Services Canada——EmpanelledPrimary source · 2025-03-20

Co-leads the smaller secure computing facility planned for government and industry research, including national-security work.

  • Programme-level disclosure
National Research Council of Canada——EmpanelledPrimary source · 2025-03-20

Co-leads the secure computing facility with Shared Services Canada. Its existing research infrastructure is also eligible for the near-term compute expansion.

  • Programme-level disclosure
Queen's University——AnnouncedPrimary source · 2026-03-26

Queen’s and Simon Fraser University signed an agreement to pursue federal supercomputer funding. Their proposed model includes Bell as an infrastructure partner and depends on securing that funding.

  • Programme-level disclosure

External dependence

NVIDIA hardware: High · US technology: High. These are editorial assessments based on the programme’s procurement disclosures.

Named partners: Digital Research Alliance of Canada, CIFAR, ISED, Canada Infrastructure Bank, NRC.

Canada’s compute strategy combines public supercomputing with support for commercial data centres and subsidies for smaller businesses’ compute purchases. The June 2026 AI for All strategy adds C$700M to the Compute Access Fund and describes proposed commercial partnerships that could supply 850 MW by 2030, with potential expansion to 2.3 GW.

Data-quality caveats on this record · 6

  • Budget 2024 provided up to C$2B over five years: C$700M for the AI Compute Challenge, C$1B for public computing infrastructure, and C$300M for the Compute Access Fund.
  • Budget 2025’s C$925.6M includes C$800M previously provided for in the fiscal framework. Its overlap with the Budget 2024 allocation is unresolved.
  • The March 2025 breakdown assigned up to C$705M to the public supercomputer and C$200M to existing infrastructure, both within the C$1B public-infrastructure envelope. A smaller secure facility was also planned, with no separate amount specified.
  • The 2026 supercomputer call proposes approximately C$890M over seven fiscal years from 2026–27 for design, construction and operation. Funding remains subject to spending authority, negotiation and a contribution agreement. Applications closed on 1 June 2026.
  • Narval’s existing configuration comprises 159 nodes with four A100 40 GB GPUs each, or 636 GPUs. The new supercomputer call gives no device count.
  • The 850 MW proposed for 2030 and potential expansion to 2.3 GW depend on commercial partnerships still being finalised in June 2026.

The evidence trail

15 cited sources

Machine accessThe same record, machine-readable: the evidence-trail feed and the derivation-chain export.