Canada sovereign AI programme

Canada had one system of 636 accelerators in operation.

Canadian Sovereign AI Compute Strategy, 2024–2030; the record also covers Pan-Canadian AI Strategy and AI for All

Accelerators636 operating
A full bar is 300,000 accelerators.

Systems

One hardware record.

The programme’s systems
In operationDigital Research AllianceA100

Funding

Budget 2024 provided up to C$2B over five years: C$700M for the AI Compute Challenge, C$1B for public computing infrastructure, and C$300M for the Compute Access Fund.

Budget 2025’s C$925.6M includes C$800M previously provided for in the fiscal framework. Its overlap with the Budget 2024 allocation is unresolved.

Money on record

state an allocation of 2 billion CAD, 2024 to 2029.

Chips and rules

Accelerators
NVIDIA’s accelerators are in its one system.Chip makers’ product pages
US export rules
Canada is in , outside the groups where exporting advanced AI chips needs a licence from the US Bureau of Industry and Security (BIS).Electronic Code of Federal Regulations, 29 Oct 2026
Scrutica’s rating
Scrutica rates the programme’s dependence on NVIDIA hardware and on US technology high, on a scale of none, low, medium and high.A qualitative assessment of the programme’s chips, partners and supplier relationships, as none, low, medium or high

Partners

9 partners by procurement stage and 4 more named in the programme’s sources.

Named in sources
CIFAR, ISED, Canada Infrastructure Bank, NRC

Sources

15 sources
SourceDate
Prime Minister’s announcement of AI for All on 4 June 2026.14 Jul 2026
AI for All: additional Compute Access Fund funding and proposed commercial compute capacity.14 Jul 2026
Former ISED supercomputer-programme address; now redirects to the department’s language-selection page.
Alliance documentation of Narval’s node configuration and A100 GPUs.8 Apr 2026
ISED’s public-infrastructure, commercial-compute and SME-access programmes.28 Mar 2026
ISED’s 5 December 2024 allocation of the C$2B compute strategy across three programmes.28 Mar 2026
Alliance response to Budget 2024’s broader C$2.4B AI package.28 Mar 2026
CIFAR’s account of the Pan-Canadian AI Strategy.28 Mar 2026
Budget 2025, “Seizing the Full Potential of Artificial Intelligence”: C$925.6M, including C$800M previously provided for.8 Sep 2026
The 2026 public-supercomputer call: approximately C$890M, funding conditions and the 1 June closing date.8 Sep 2026
ISED’s 20 March 2025 announcement of the Cohere contribution and revised compute-programme allocations.8 Sep 2026
ISED environmental assessment identifying Cohere as anchor tenant and CoreWeave as facility builder and operator; issued 5 June 2026.8 Sep 2026
The Alliance’s 18 February 2025 announcement of its Australian partnership and scheduled C$85M funding.8 Sep 2026
Amii’s 25 July 2025 account of PAICE’s institute–university partnerships and the Vulcan launch.8 Sep 2026
Queen’s 26 March 2026 announcement of its proposed collaboration with Simon Fraser University and Bell.8 Sep 2026
Data
How the figures were made

Operating compute / delivered hardware. Reported operational or delivered: 636 NVIDIA A100 SXM4 (40GB) (physical hardware). The stage is assigned from reported hardware status, disbursements and commitments.

Canada’s compute strategy combines public supercomputing with support for commercial data centres and subsidies for smaller businesses’ compute purchases. The June 2026 AI for All strategy adds C$700M to the Compute Access Fund and describes proposed commercial partnerships that could supply 850 MW by 2030, with potential expansion to 2.3 GW.

Other caveats on this record, 4

  • The March 2025 breakdown assigned up to C$705M to the public supercomputer and C$200M to existing infrastructure, both within the C$1B public-infrastructure envelope. A smaller secure facility was also planned, with no separate amount specified.
  • The 2026 supercomputer call proposes approximately C$890M over seven fiscal years from 2026–27 for design, construction and operation. Funding remains subject to spending authority, negotiation and a contribution agreement. Applications closed on 1 June 2026.
  • Narval’s existing configuration comprises 159 nodes with four A100 40 GB GPUs each, or 636 GPUs. The new supercomputer call gives no device count.
  • The 850 MW proposed for 2030 and potential expansion to 2.3 GW depend on commercial partnerships still being finalised in June 2026.
Identifiers
Scrutica ID
sovereign-ca
Country code
CA
Name in the record