Sovereign AI
Sovereign programme record · Poland · 2025–2028
Poland: programme funding and hardware
Poland: PIAST-AI Factory (EuroHPC) + PSNC
The reconciliation
This record has no dollar amount for these funding stages. Programme details and source amounts appear below.
Announcement recorded. No commitment or disbursement recorded.
Hardware on record
Empanelled partners · 4
| Partner | Accelerators | Model | Stage | Source |
|---|---|---|---|---|
| Poznańskie Centrum Superkomputerowo-Sieciowe (PSNC) | — | — | — | Primary source · 2025-06-23 |
PSNC signed the PIAST-AI hosting agreement in June 2025 and planned more than 1,000 GPUs. Its staff’s June 2026 account targets new-infrastructure procurement in 2027 and full operation in 2028. | ||||
| Poznan University of Technology | — | — | Empanelled | Primary source · 2025-06-23 |
Named by PSNC in June 2025 as a PIAST-AI consortium member; the university also took part in the May 2026 procurement and project-planning meeting. | ||||
| Adam Mickiewicz University in Poznań | — | — | Empanelled | Primary source · 2025-06-23 |
Named by PSNC in June 2025 as a PIAST-AI consortium member; the university also took part in the May 2026 procurement and project-planning meeting. | ||||
| Nicolaus Copernicus University in Toruń | — | — | Empanelled | Primary source · 2025-06-23 |
Named by PSNC in June 2025 as a PIAST-AI consortium member; the university also took part in the May 2026 procurement and project-planning meeting. | ||||
External dependence
NVIDIA hardware: Unknown · US technology: High. These are editorial assessments based on the programme’s procurement disclosures.
Named partners: PSNC, Poznan University of Technology, Adam Mickiewicz University, Nicolaus Copernicus University, EuroHPC JU, Polish Ministry of Digital Affairs.
PSNC leads PIAST-AI with Poznań University of Technology, Adam Mickiewicz University and Nicolaus Copernicus University. A June 2026 account by PSNC staff describes a €100 million investment, with new-infrastructure procurement planned for 2027 and full operation for 2028. Existing PSNC computing platforms already support AI models and services. Poland also participates in the LUMI AI Factory consortium.
Data-quality caveats on this record · 3
- PSNC’s June 2025 hosting announcement planned more than 1,000 GPUs without naming a model. The June 2026 account gives a later implementation schedule but no revised GPU specification.
- CORDIS lists €12.5 million in total project costs and a €6.25 million EU contribution for PIAST AIF, running from May 2026 to April 2029. The sources do not itemise how this grant relates to the €100 million infrastructure investment described by PSNC staff.
- The June 2025 hosting agreement establishes PSNC’s role. The May 2026 consortium update discusses GPU procurement without naming an awarded hardware supplier.
The evidence trail
7 cited sources- PSNC: June 2025 hosting agreement, consortium and planned GPU capacity — Primary source · accessed 2026-09-08
- EuroHPC: March 2025 PIAST-AI selection — Primary source · accessed 2026-09-08
- EuroHPC: PIAST-AI services and consortium infrastructure — Primary source · accessed 2026-09-08
- PSNC: May 2026 review of GPU procurement and project work packages — Primary source · accessed 2026-09-08
- PSNC staff: June 2026 infrastructure budget, procurement in 2027 and full operation in 2028 — Primary source · accessed 2026-09-08
- CORDIS: PIAST AIF grant 101250730, project costs, EU contribution and 2026–29 term — Primary source · accessed 2026-09-08
- EuroHPC: Poland’s participation in the LUMI AI Factory consortium — Primary source · accessed 2026-09-08