TypeAI TrainingStatusUnder constructionWhereAbu Dhabi, AEIndexed fromCompany disclosure (press / IR)

G42 announced planned OpenAI and Oracle operation of the 1 GW Stargate UAE cluster

The announcement places this cluster within a 5 GW campus. It does not establish Oracle as the sole operator of the entire campus or confirm that operation has begun.

Role disclosure: “Stargate UAE, a 1-gigawatt compute cluster, will be built by G42 and operated by OpenAI and Oracle.”

Stargate UAE: 5 GW AI campus in Masdar City, Abu Dhabi. Partnership between OpenAI, G42, Oracle, NVIDIA, SoftBank, and Cisco. First 200 MW cluster expected live 2026; Phase 1 (1 GW) by end of 2027. Campus spans ~10 square miles. Dedicated power: natural gas turbines (baseload), 1.5 GW solar array, battery storage, backup from Barakah nuclear plant. Total investment: ~$30B.

Source: Company disclosure (press / IR)

1/3site roles identified0 site relationships1 finding in the company chain0 export-control designationsFurthest finding: company at site

Date in site records: May 22, 2025. Site data: Company disclosure (press / IR).

Ownership and operation

Plate I. Site owner, operator and hardware ownerscrutica.com · data to May 22, 2025 (derived)

Site operator · announced

Oracle Corporation parent ownership unresolved 1 finding

Which organisation runs it?

Stargate UAE (OpenAI/G42/Oracle)Site

Site operator · announced Oracle Corporation. “Stargate UAE, a 1-gigawatt compute cluster, will be built by G42 and operated by OpenAI and Oracle.” source

Companies are grouped by their role at the site, with recorded parents above them. No parent companies were found in the ownership data. Further ownership remains unresolved where labelled. Record source: Company disclosure (press / IR); authority tier 2. Each role is drawn only as the relationship its own source establishes, listed above; none implies exclusive control of the full site. Ticks count the export-control and government-link findings for each company.

Export controls and government links

No export-control designations were found in the checked company chains.

Plate III. Export controls and government linksscrutica.com · data to May 22, 2025 (derived)
site1A company in the ownership chain is headquartered in the United Statescompany levels
Company at site

Headquarters jurisdiction
A company in the ownership chain is headquartered in the United States

United States: Operates the Export Administration Regulations (EAR) and the BIS Entity List under 15 CFR 730–774; deemed-export rules extend reach to foreign nationals on US soil. Export-control regimes listed for this jurisdiction: Wassenaar Arrangement, US EAR (BIS Entity List authority).

Country is the recorded headquarters location.Linked through the company named as the planned operator of this site.

Triangle: export-control designation or regulatory flag. Square: sovereign capital linkage. Circle: headquarters jurisdiction. Level 1 is a company at the site; higher levels are its parents. 1 finding is recorded; 0 are export-control designations.

Capacity

Reading. Power and acceleratorsscrutica.com · data to May 22, 2025 (derived)
5.0 GW

Facility power

Estimated. Not operating capacity: campus envelope on a site not yet operating.

not recorded

Power for IT equipment

not recorded

Accelerators

Stargate UAE / Abu Dhabi 5GW AI Campus (OpenAI / G42 / Oracle) has 5 records, and their power figures are never added together. Across the platform, recorded totals count the marked figure once; operating totals count a member’s figure only if it is operating capacity. Measurement scope is unrecorded for 1 of them.

Scope: announced campus envelope · Status: under construction · counted in recorded totals

Stargate UAE (OpenAI/G42/Oracle)

5.0 GW · not operating capacity · Company disclosure (press / IR)

Scope: not stated · Status: under construction

OpenAI Stargate UAE

no power figure · Epoch AI Frontier Data Centers

Scope: announced campus envelope · Status: announced

Abu Dhabi UAE/USA 5GW Campus Phase 2

5.0 GW · not operating capacity · Epoch AI GPU Clusters

Scope: named cluster (phase 1) · Status: announced

Stargate UAE Phase 1

200 MW · not operating capacity · Epoch AI GPU Clusters

Scope: named cluster (phase 2) · Status: announced

Stargate UAE Phase 2

1.0 GW · not operating capacity · Epoch AI GPU Clusters

Methods and sources

Ownership roles

Title identifies the legal owner of the site; operation identifies who runs it. AI-hardware ownership follows the catalog’s attribution of the machines inside, whose owner may lease the facility.

Each role requires its own attribution. An operator named in a source supplies evidence of operation only.

Parent companies

Ownership checks start with each company named at the site and follow recorded parent relationships. A company holding several roles is checked once. Its linked company page lists the relationships and their sources; further parents may remain undocumented.

Level 1 identifies a company at the site, level 2 its parent, and each further level another parent. Export-control designations and government investments are assigned to the company concerned.

Missing values

Unrecorded roles remain blank. Findings whose company position is unresolved stay in the list with that position labelled unknown.

Publication limits

Subscription corporate data helps identify parent relationships and sovereign investments. Publication is limited to relationship classes and supporting public sources; licensed records, identifiers and values are withheld.

Curator’s note on this campus

Five records describe the announced 5 GW Abu Dhabi campus programme and projects within it. Recorded totals count the 5,000 MW campus envelope once; no member is operating, so operating totals exclude the campus. Stargate UAE is the approximately 1 GW anchor project; the cited reporting targeted its first approximately 200 MW cluster for 2026. The full 5 GW envelope should not be read as capacity already under construction. The duplicate 5,000 MW estimate and the 200 MW and 1,000 MW phase figures remain visible for comparison but are excluded from both totals.