Skip to main content

OpenAI Stargate Abilene Oracle OCI Supercluster Phase 2

TypeAI TrainingStatusAnnouncedWhereAbilene, USIndexed fromEpoch AI GPU Clusters

Announced; Oracle Corporation is recorded as owning the AI hardware inside this site

1/3site roles identified0 site relationships1 finding in the company chain0 export-control designationsFurthest finding: company at site

Site data: Epoch AI GPU Clusters.

Ownership and operation

Plate I. Site owner, operator and hardware ownerscrutica.com · compiled Oct 25, 2026

AI hardware owner · per catalog

Oracle Corporation parent ownership unresolved 1 finding

Which organisation owns the AI hardware inside it?

OpenAI Stargate Abilene Oracle OCI Supercluster Phase 2Site

AI hardware owner · per catalog Oracle Corporation. Epoch AI's field for who owns the AI hardware, which it defines as not necessarily the owner or operator of the facility. source

Companies are grouped by their role at the site, with recorded parents above them. No parent companies were found in the ownership data. Further ownership remains unresolved where labelled. Record source: Epoch AI GPU Clusters; authority tier 2. Each role is drawn only as the relationship its own source establishes, listed above; none implies exclusive control of the full site. Ticks count the export-control and government-link findings for each company.

Export controls and government links

No export-control designations were found in the checked company chains.

Plate III. Export controls and government linksscrutica.com · compiled Oct 25, 2026
site1A company in the ownership chain is headquartered in the United Statescompany levels
Company at site

Headquarters jurisdiction
A company in the ownership chain is headquartered in the United States

United States: Operates the Export Administration Regulations (EAR) and the BIS Entity List under 15 CFR 730–774; deemed-export rules extend reach to foreign nationals on US soil. Export-control regimes listed for this jurisdiction: Wassenaar Arrangement, US EAR (BIS Entity List authority).

Country is the recorded headquarters location.Linked through the company recorded as owning the AI hardware inside this site.

Triangle: export-control designation or regulatory flag. Square: sovereign capital linkage. Circle: headquarters jurisdiction. Level 1 is a company at the site; higher levels are its parents. 1 finding is recorded; 0 are export-control designations.

Capacity

Reading. Power and acceleratorsscrutica.com · compiled Oct 25, 2026
801 MW

Facility power

Excluded from totals to avoid counting this campus twice; the total uses Stargate Abilene (OpenAI/Oracle/SoftBank).

not recorded

Power for IT equipment

300,001

Accelerators

269,328 H100-equivalent. Not operating capacity: announced.

Present inventory by partition

withheld Facility status is announced, not operational.

  1. 200,001 × NVIDIA GB300 (Blackwell Ultra) (estimated)

    status not stated (from the facility status)

    Held: Not present capacity. Part of the inventory has no recognized deployment status.

    Catalogue row; no partition-level source recorded

  2. 100,000 × NVIDIA GB200 (estimated)

    status not stated (from the facility status)

    Held: Not present capacity. Part of the inventory has no recognized deployment status.

    Catalogue row; no partition-level source recorded

2 partitions are held, so no facility figure is derived; the held partitions’ counts and sources remain visible and nothing is substituted for their rates. Rates are the cited dense FP16 figure per accelerator; the sum applies the methodology’s utilization and interconnect assumptions and is a theoretical aggregate, not one job’s throughput. The catalogue figures above are the record’s scalar fields (the source’s transcription, or its recorded correction) and are a different basis.

Stargate Abilene (OpenAI / Oracle / Crusoe) has 5 records, and their power figures are never added together. Across the platform, recorded totals count the marked figure once; operating totals count a member’s figure only if it is operating capacity.

Scope: announced site scope · Status: operational · counted in recorded totals

Stargate Abilene (OpenAI/Oracle/SoftBank)

1.2 GW · not operating capacity · Company disclosure (press / IR)

Scope: current deployment · Status: operational

OpenAI Stargate Abilene

590 MW · operating capacity · Epoch AI Frontier Data Centers

Scope: named cluster (phase 1) · Status: announced

OpenAI Stargate Abilene Oracle OCI Supercluster Phase 1

240 MW · not operating capacity · Epoch AI GPU Clusters

Scope: named cluster (phase 2) · Status: announced

OpenAI Stargate Abilene Oracle OCI Supercluster Phase 2

801 MW · not operating capacity · Epoch AI GPU Clusters

Scope: named cluster (phase 3) · Status: announced

OpenAI Stargate Abilene Oracle OCI Supercluster Phase 3

2.2 GW · not operating capacity · Epoch AI GPU Clusters

Data quality · 1 flag
  • Any power figure on this record is excluded from power totals to avoid counting overlapping campus capacity twice.
    Curator’s working note

    Part of campus Stargate Abilene (OpenAI / Oracle / Crusoe). This row's power capacity is withheld from aggregates; the campus canonical power figure lives on Stargate Abilene (OpenAI/Oracle/SoftBank). See the campus source-disagreement panel for every cited figure.

Methods and sources

Ownership roles

Title identifies the legal owner of the site; operation identifies who runs it. AI-hardware ownership follows the catalog’s attribution of the machines inside, whose owner may lease the facility.

Each role requires its own attribution. An operator named in a source supplies evidence of operation only.

Parent companies

Ownership checks start with each company named at the site and follow recorded parent relationships. A company holding several roles is checked once. Its linked company page lists the relationships and their sources; further parents may remain undocumented.

Level 1 identifies a company at the site, level 2 its parent, and each further level another parent. Export-control designations and government investments are assigned to the company concerned.

Missing values

Unrecorded roles remain blank. Findings whose company position is unresolved stay in the list with that position labelled unknown.

Publication limits

Subscription corporate data helps identify parent relationships and sovereign investments. Publication is limited to relationship classes and supporting public sources; licensed records, identifiers and values are withheld.

Epoch AI estimates capacity using satellite imagery, permits and corporate disclosures. Its catalog is the source for this site record.

Curator’s note on this campus

Five records describe the Abilene campus at different scopes. Recorded totals use the 1,200 MW site figure from OpenAI’s Stargate announcement, which describes the announced site rather than the plant running today. Operating totals use Epoch’s current-deployment estimate instead; Epoch’s April 2026 analysis estimated four of the eight buildings operational. The announced cluster-phase figures of 240.24, 800.80 and 2,200 MW remain visible but are excluded from both totals. The archived source does not establish whether the phases are additive or cumulative. The 2,200 MW phase figure exceeds the 1,200 MW site figure and requires a site-level source to resolve the difference.

Browse the facilities directory or search the company directory.