Capacity, hardware inventory, ownership chain, and supply-chain position for STACK Infrastructure NVA02. Any export-control exposure is walked through the canonical organization graph — surfacing when the BIS Entity List touches a node above the facility in the chain — rather than asserted at the facility row.
As of 2026-07-27
Description
Stack Infrastructure NVA02 is a 10-building (6 for AI) data center campus, with a future IT power capacity of 350 MW for AI. Construction began Q4 2019, with their non-AI buildings finishing by Q4 2022. Construction ramped up in 2023, with the first high-density AI data center (containing two independent halls) becoming operational Q4 2024. Their progress indicates a 2028 finish date for the six total AI data centers.
Notes
Total capital cost (2025 USD): $3.22B | Epoch estimation methods: our cooling equipment power model, chip availability, chip efficiency, company disclosures.