Skip to main content

CoreWeave Muskogee

TypeAI TrainingStatusAnnouncedWhereOklahoma 35.693709, USIndexed fromEpoch AI GPU Clusters

Announced; CoreWeave is recorded as owning the AI hardware inside this site

1/3site roles identified0 site relationships1 finding in the company chain0 export-control designationsFurthest finding: company at site

Site data: Epoch AI GPU Clusters.

Ownership and operation

Plate I. Site owner, operator and hardware ownerscrutica.com · compiled Oct 25, 2026

AI hardware owner · per catalog

CoreWeave parent ownership unresolved 1 finding

Which organisation owns the AI hardware inside it?

CoreWeave MuskogeeSite

AI hardware owner · per catalog CoreWeave. Epoch AI's field for who owns the AI hardware, which it defines as not necessarily the owner or operator of the facility. source

Companies are grouped by their role at the site, with recorded parents above them. No parent companies were found in the ownership data. Further ownership remains unresolved where labelled. Record source: Epoch AI GPU Clusters; authority tier 2. Each role is drawn only as the relationship its own source establishes, listed above; none implies exclusive control of the full site. Ticks count the export-control and government-link findings for each company.

Export controls and government links

No export-control designations were found in the checked company chains.

Plate III. Export controls and government linksscrutica.com · compiled Oct 25, 2026
site1A company in the ownership chain is headquartered in the United Statescompany levels
Company at site

Headquarters jurisdiction
A company in the ownership chain is headquartered in the United States

United States: Operates the Export Administration Regulations (EAR) and the BIS Entity List under 15 CFR 730–774; deemed-export rules extend reach to foreign nationals on US soil. Export-control regimes listed for this jurisdiction: Wassenaar Arrangement, US EAR (BIS Entity List authority).

Country is the recorded headquarters location.Linked through the company recorded as owning the AI hardware inside this site.

Triangle: export-control designation or regulatory flag. Square: sovereign capital linkage. Circle: headquarters jurisdiction. Level 1 is a company at the site; higher levels are its parents. 1 finding is recorded; 0 are export-control designations.

Capacity

Reading. Power and acceleratorsscrutica.com · compiled Oct 25, 2026
100 MW

Facility power

Estimated. Not operating capacity: announced.

not recorded

Power for IT equipment

~40,000

Accelerators

Estimated from power capacity. 101,061 H100-equivalent. Not operating capacity: announced.

Present inventory by partition

withheld Facility status is announced, not operational.

  1. 40,000 × NVIDIA GB200 (estimated)

    status not stated (from the facility status)

    Held: Not present capacity. Part of the inventory has no recognized deployment status.

    Catalogue row; no partition-level source recorded

One partition is held, so no facility figure is derived; the held partition’s count and source remain visible and nothing is substituted for its rate. Rates are the cited dense FP16 figure per accelerator; the sum applies the methodology’s utilization and interconnect assumptions and is a theoretical aggregate, not one job’s throughput. The catalogue figures above are the record’s scalar fields (the source’s transcription, or its recorded correction) and are a different basis.

CoreWeave Muskogee, OK has 2 records, and their power figures are never added together. Across the platform, recorded totals count the marked figure once; operating totals count a member’s figure only if it is operating capacity. Measurement scope is unrecorded for 2 of them.

Scope: not stated · Status: announced · counted in recorded totals

CoreWeave Muskogee

100 MW · not operating capacity · Epoch AI GPU Clusters

Scope: not stated · Status: under construction

CoreWeave Muskogee OK

no power figure · Epoch AI Frontier Data Centers

Power comparison

100 MW is not placed among operating AI Training figures (announced).

Data quality · 1 flag
  • The accelerator count is an estimate derived from power capacity, not a hardware inventory. The displayed chip count, 40,000 GPUs, is inferred from the source's power figure of 100 MW: Epoch AI's GPU Clusters dataset marks the count as roughly estimated from power, so it is neither an operator disclosure nor an export-control authorization, and a power-derived count is not an installed inventory. No primary source supplies the facility's own count, so the recorded figure stands as the source gives it and this flag marks it as an estimate. The group of records was identified on 19 May 2026 and flagged on 14 July 2026.

Methods and sources

Ownership roles

Title identifies the legal owner of the site; operation identifies who runs it. AI-hardware ownership follows the catalog’s attribution of the machines inside, whose owner may lease the facility.

Each role requires its own attribution. An operator named in a source supplies evidence of operation only.

Parent companies

Ownership checks start with each company named at the site and follow recorded parent relationships. A company holding several roles is checked once. Its linked company page lists the relationships and their sources; further parents may remain undocumented.

Level 1 identifies a company at the site, level 2 its parent, and each further level another parent. Export-control designations and government investments are assigned to the company concerned.

Missing values

Unrecorded roles remain blank. Findings whose company position is unresolved stay in the list with that position labelled unknown.

Publication limits

Subscription corporate data helps identify parent relationships and sovereign investments. Publication is limited to relationship classes and supporting public sources; licensed records, identifiers and values are withheld.

Epoch AI estimates capacity using satellite imagery, permits and corporate disclosures. Its catalog is the source for this site record.

Curator’s note on this campus

Two Epoch records describe the Core Scientific site at Muskogee, with CoreWeave as tenant. Recorded totals use the 100 MW cluster record; the other record has no power figure. Neither record is operating, so operating totals include no power from this site. Core Scientific’s 18 November 2024 release describes 100 MW of facility power and approximately 70 MW of critical IT load. Its 6 May 2026 filing separately describes the Polaris acquisition and 440 MW of contracted power; whether Polaris belongs to this campus remains unresolved in the sources reviewed.

Browse the facilities directory or search the company directory.