No corporate parent is shown
- Scrutica id
- org-fermi-inc
- SEC CIK
- 2071778
- Ticker
- FRMI
Ownership chain
No corporate parent is shown for Fermi Inc. Shareholder concentration requires separate shareholding data.
Compute arrangements
Filings and announcements recording who owns, runs or contracts compute capacity, where Fermi Inc. is one of the parties: 1 disclosure. Each is graded by its source’s authority, who disclosed it and whether its figure is an estimate.
Receipt
“222 megawatts (MW) of total facility power... approximately $6.5 billion in total contracted revenue... initial 15-year term, for the first phase, excluding any renewal terms... tens of thousands of next-generation AMD Instinct GPUs.”
Project Matador, Carson County, Texas. The lease names Fermi Campus 1 LLC as lessor and TensorWave TEX1, LLC as lessee, with expansion rights beyond 650 MW and delivery expected from the second half of 2027. The linked source reproduces Fermi’s announcement.
Fermi’s second-quarter 2026 Form 10-Q: TensorWave lease terms ↗
Related analysis
Geographic revenue, business segments and capital allocation are unavailable from the licensed financial dataset. The public industry classification (SIC, NAICS) is also unrecorded. Sources and publication limits.