# Neocloud Landscape
## 84 per cent of the neocloud fleet is not built yet

01,0002,0003,000megawatts recordedH100-equivalents, where statedCrusoe — 2 facilities, 2,800 MW recorded across 2 of themCrusoe2 sites—IREN Limited — 4 facilities, 2,751 MW recorded across 4 of themIREN Limited4 sites816 · 1/4 sitesCoreWeave — 12 facilities, 803 MW recorded across 9 of themCoreWeave12 sites · 3 state no capacity1,158,959 · 10/12 sitesTeraWulf — 1 facilities, 510 MW recorded across 1 of themTeraWulf1 site—Nebius — 7 facilities, 433 MW recorded across 5 of themNebius7 sites · 2 state no capacity493,682 · 7/7 sitesApplied Digital — 3 facilities, 400 MW recorded across 1 of themApplied Digital3 sites · 2 state no capacity846,387 · 3/3 sitesTogether AI — 2 facilities, 93 MW recorded across 2 of themTogether AI2 sites95,379 · 2/2 sitesLambda Labs — 1 facilities, 46 MW recorded across 1 of themLambda Labs1 site32,000 · 1/1 siteVoltage Park — 7 facilities, 34 MW recorded across 6 of themVoltage Park7 sites · 1 state no capacity25,528 · 7/7 sitesVultr — 1 facilities, 5 MW recorded across 1 of themVultr1 site3,964 · 1/1 site

announced — 6,595 MWoperational — 1,280 MW

1,280

megawatts operating, of 7,875 recorded across 10 fleets; the rest is announced. **CoreWeave** has the largest built fleet at 703 MW.

40

facilities in which a rostered neocloud is the recorded AI-hardware owner, across 4 countries. 32 state a capacity. The remainder are drawn nowhere on the axis, because a missing figure is not a zero.

2,656,715

H100-equivalent accelerators, summed over the 32 facilities that state a count. That denominator is the figure’s own coverage limit: the total is a floor.

_The neocloud fleet._ One bar per company, length in megawatts of recorded data-center capacity, segmented by build status: solid where a site is recorded as operational, half-toned under construction, and outlined where it is announced. The role drawn is AI-hardware ownership, Epoch AI’s field for who owns the accelerators inside a data center, which Epoch states is not necessarily the facility’s owner or operator. For a neocloud that is the right role, since the business is owning hardware inside somebody else’s building: a bar here is a fleet of machines, whatever building houses them. Announced capacity is drawn as an outline and never summed into a delivered figure. Facilities that state no capacity appear nowhere on the axis and are counted separately in the row, because a missing megawatt figure is not a zero. The accelerator column has its own denominator for the same reason.

AI-focused clouds promise to widen compute access beyond the hyperscalers. Across 10 of them the substrate records 40 facilities in 4 countries where the company owns the AI hardware, and 1,280 of 7,875 recorded megawatts are operating today. The gap between those two numbers is the neocloud question: capacity announced at this scale is a claim on future supply, and the upstream chokepoints on [Chokepoints](/supply-chain/chokepoints) constrain those claims.

### Supplier rows held under license

Whether neoclouds diversify supply or inherit it is answered by their supplier sets: if every one of them buys from the same short list, a single upstream disruption reaches all of them at once. Scrutica records 57 relationship rows involving these companies, and 16 of them (28 per cent) are publishable. The other 41 arrive from a [licensed database](/methodology#licensed-substrate) held under subscription and not redistributed.

A shared-supplier figure drawn from the publishable remnant alone would measure what happens to be publishable, so none is drawn. The counts above are corpus metadata, which is licensing-safe; the withheld rows inform the aggregate denominators on [the dependency graph](/supply-chain) and are published nowhere. The public subset is enumerated below.

### The public relationship subset

Cite

CSVJSONJSON+Prov

PrintScreenshot

Bilateral relationships between these companies and their counterparties, on the public-provenance subset only. Read it as a sample of a larger graph; the ratio above is the sampling fraction.

Loading supply chain data...