# River Bend Data Center Campus

Facility record `fac-hut8-river-bend` — data source: SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1964789/000110465926053247/tm2613163d1_8k.htm); authority tier 1

| Field | Value |
| --- | --- |
| Type | AI Training |
| Status | Under construction |
| Location | St. Francisville, Louisiana, US (30.71231, -91.31198) |
| Facility power | 330 MW |
| Power is operating capacity | no (under construction) |
| IT load | 245 MW |
| GPU count | not published |
| H100-equivalents | not published |
| Peak PFLOPS (FP16) | not published |
| Site owner | The site owner is unrecorded. |
| Site operator | No organisation is recorded as operating this site. |
| AI hardware owner | No AI-hardware owner is recorded for this site. |
| Announced | not published |
| Operational | not published |

Hut 8's AI data centre campus off LA 964 near St. Francisville in West Feliciana Parish, Louisiana, with 330 MW of utility capacity and 245 MW of critical IT capacity leased for 15 years to Fluidstack, with Google backstopping the lease payments. Vertical construction began in the second quarter of 2026, and Hut 8 targets the first data hall for the second quarter of 2027.

Source: [SEC EDGAR](<https://www.sec.gov/Archives/edgar/data/1964789/000110465926053247/tm2613163d1_8k.htm>)