# Meta Temple

Facility record `fac-epoch-meta-temple` — data source: epoch-ai (https://epoch.ai/data/data-centers); authority tier 2; contains estimated values (is_estimated: true)

| Field | Value |
| --- | --- |
| Type | ai training |
| Status | operational |
| Location | Temple, Texas, US (31.131111, -97.37) |
| Power capacity | 152 MW |
| IT load | not published |
| GPU count | not published |
| Peak PFLOPS (FP16) | not published |
| Owner | Meta Platforms, Inc. |
| Operator | Meta Platforms, Inc. |
| Announced | not published |
| Operational | not published |

Meta Temple is notable for a mid-flight change in construction. A traditional H-shaped Meta data center was partially built on the site by 2023, only to be demolished in favor of Meta's new AI-optimized data center design. The power capacity of the new design was reported by construction company JE Dunn, and is backed up by our cooling model. Later, a third data center building was added to the plan. Compute capacity assumes that NVIDIA GB300 NVL72 servers are used, as these are the most popular

## Data-quality flags

- source_url_contains_claim_verified
- duplicate_name_ambiguous_same_site

## Cite

> Scrutica, "Meta Temple" (facility record), https://scrutica.com/facilities/fac-epoch-meta-temple; data source: epoch-ai; accessed 2026-07-27.

Full interactive record: https://scrutica.com/facilities/fac-epoch-meta-temple · Methodology for derived values: https://scrutica.com/methodology#flop-estimation · All programmatic surfaces: https://scrutica.com/agents